Monday 21 August 2017

Centre gives more power to BRO for border road construction amid Doklam standoff

Concerns mount as BRO is far behind schedule in constructing 73 approved Indo-China border roads

Border Roads Organisation

With the Border Roads Organisation (BRO) far behind schedule in constructing 73 approved “Indo-China Border Roads” along the northern borders, the defence ministry on Sunday empowered BRO officials with enhanced financial powers.

The Chief Engineers, key officials who head BRO projects spread across the border states – with project names like Himank (Ladakh), Vartak (Arunachal Pradesh) and Beacon (Kashmir) – will now enjoy enhanced financial powers that are 5-10 times more than their earlier financial limits.
The defence ministry states this will “avoid delays on account of references between the Chief Engineer and HQ DGBR (Headquarters, Director General Border Roads) and also between HQ DGBR and the Ministry.”(economy news)

BRO’s road building has lagged, while China has constructed a wide-spread network of roads that allow their troops to reach the border quickly on vehicles. In contrast, Indian foot patrols must march long distances to reach the same areas.

With only 27 roads completed of the 73 “strategic roads” approved for the Sino-Indian border, the defence minister assured Parliament on July 28 that the balance roads would be completed by December 2022.

The earlier financial powers permitted a Chief Engineer to approval “departmental works” up to Rs 10 crore, and the ADGBR (Assistant Director General Border Roads) up to Rs 20 crore. All “contractual works” had to be referred to the DGBR, who could sanction expenditure only up to Rs 50 crore...READ MORE


 

No comments:

14th BRICS summit to review current global issues, reach key agreements

  At the   14th BRICS summit   which is to be hosted by China in a virtual mode on 23-24 June, the member nations will review the current gl...