Wednesday 4 July 2018

With on-time delivery, L&T stakes claim to build warships and submarines

Industry analysts say L&T is demonstrating its capability in order to position itself for the coming multi-billion dollar Project 75-I contract to build six new submarines
 lt-financial-services1
Underlining its capability of building complex warships and delivering them faster than other private shipyards, and even the four defence public sector undertaking (DPSU) yards, Larsen & Toubro Shipbuilding on Tuesday laid the keels of two “new generation offshore patrol vessels” (NG-OPVs) ahead of its contracted schedule.
This is part of an Indian Coast Guard (ICG) order for seven OPVs that L&T won in 2015. It stipulates delivery between 2018-2021, but L&T is determined to deliver all of them early, breaking with defence shipyards’ long tradition of late delivery.
“The first OPV [named ICGS Vikram]… was delivered in April 2018, ahead of schedule. The second OPV, launched in January 2018, is being readied for sea trials and is planned to be delivered ahead of schedule shortly,” said an L&T press release on Tuesday.
Industry analysts say L&T is demonstrating its capability in order to position itself for the coming multi-billion dollar Project 75-I contract to build six new submarines. The defence ministry plans to entrust this to the private sector under the “strategic partner” (SP) programme.
For several years, L&T told the defence ministry it would build the six Project 75-I submarines in its Hazira shipyard, where it built hull sections for the navy’s Arihant-class indigenous nuclear submarines. When the ministry argued that Hazira was too shallow, L&T spent Rs 50 billion on building a spanking new, 900-acre shipyard at Kathupalli, near Chennai, to pursue its warship building ambitions.
“With a long term commitment to the defence sector, we have made huge investments in Kattupalli shipyard and seven other dedicated defence production units to serve the nation,” said L&T chief, SN Subrahmanyan, on Tuesday.
L&T does not face serious competition from India’s 22 other private shipyards, most of which are small shipyards that cannot build large vessels. Just four have the capacity and capability to build warships, but two of those — Bharti and ABG – are insolvent. The other two – L&T and Reliance Defence’s Pipavav shipyard – run at a loss, but are kept afloat by their parent companies’ deep pockets.
Meanwhile, the defence ministry channels most major warship orders to four DPSU shipyards – Mazagon Dock Ltd, Mumbai, Garden Reach Shipbuilders & Engineers, Kolkata, Goa Shipyard Ltd, Hindustan Shipyard Ltd – and to Kerala state PSU, Cochin Shipyard Ltd, which has a dock large enough to build aircraft carriers.
L&T, however, intends to challenge this established order. It is building a ICG order for 54 fast interceptor boats. Earlier this month, it delivered the 39th and 40th of these boats, two years ahead of schedule. In March, L&T delivered to the navy India’s first indigenously designed and built “floating dock” which is used for repairing warships and submarines of upto 8,000 tons displacement..Click Here : Larsen & Turbo Share Price

No comments:

14th BRICS summit to review current global issues, reach key agreements

  At the   14th BRICS summit   which is to be hosted by China in a virtual mode on 23-24 June, the member nations will review the current gl...